When using a fixed-price./lump-sum contract, which of the following; situations can a payment be made for the adjustment of fluctuations in the cost of of construction resources?
In a fixed-price/lump-sum contract, the agreed price is fixed and generally not subject to adjustment based on fluctuations in costs, unless explicitly stated in the contract terms. Payment for adjustments in construction costs due to fluctuations in resource prices or delays is typically not allowed unless there is a specific provision for such adjustments, which is rare in fixed-price contracts. Therefore, the correct answer is C. In no situation.
Top of Form
Bottom of Form
Veronica
1 months agoDortha
1 months agoBrinda
9 days agoVerona
9 days agoAnnice
24 days agoAleisha
1 months agoNa
7 days agoAnnelle
13 days agoRasheeda
23 days agoMindy
1 months agoNakita
6 days agoLaticia
16 days agoTimothy
17 days agoKati
28 days agoAndrew
1 months agoChau
2 months agoAndrew
2 months ago