Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam CCP Topic 3 Question 11 Discussion

Actual exam question for AACE International's CCP exam
Question #: 11
Topic #: 3
[All CCP Questions]

Which of the following is NOT an advantage specific to a cost reimbursable contract?

Show Suggested Answer Hide Answer
Suggested Answer: D

In a cost reimbursable contract, the contractor is reimbursed for all allowable costs incurred during the project, plus an additional fee (which could be a fixed fee or a percentage of costs). This contract type provides several advantages but also has its limitations.

Key Points:

Advantages of Cost Reimbursable Contracts:

Simpler Proposal Evaluation: The focus is on selecting the best contractor rather than the lowest bid, making the evaluation process simpler.

Flexibility in Dealing with Changes: This contract type allows for adjustments and changes as the project progresses.

Early Start: Work can begin quickly without needing a fully defined scope since costs are reimbursed.

Owner Control:

While cost reimbursable contracts offer flexibility, they do not inherently mean that the owner controls all aspects of the work. The contractor typically manages the execution of the project, while the owner retains control over the budget and major decisions.

Conclusion: The correct answer is D. Owner controls all aspects of the work because, in cost reimbursable contracts, the contractor has significant control over how the work is performed, while the owner mainly controls costs and high-level decisions.


Contribute your Thoughts:

Wilda
2 months ago
Owner controls all aspects of the work? Sounds like a recipe for a micromanager's dream. No thanks!
upvoted 0 times
Marion
10 days ago
C) An early start can be made
upvoted 0 times
...
Penney
16 days ago
B) Provides flexibility in dealing with changes
upvoted 0 times
...
Vi
17 days ago
A) Evaluation of proposals are much simpler
upvoted 0 times
...
...
Arlie
2 months ago
Cost reimbursable contracts? More like 'cost reimbursable headaches', am I right? *chuckles*
upvoted 0 times
Annamaria
25 days ago
C) An early start can be made
upvoted 0 times
...
Noel
1 months ago
B) Provides flexibility in dealing with changes
upvoted 0 times
...
Kiley
1 months ago
A) Evaluation of proposals are much simpler
upvoted 0 times
...
...
Rozella
2 months ago
This question is as clear as mud. I guess I'll just throw a dart and hope for the best.
upvoted 0 times
...
Lazaro
2 months ago
An early start can be made? That's a good one, but I'm not falling for it. Gotta go with A on this one.
upvoted 0 times
Nadine
1 months ago
Definitely not C, An early start can be made.
upvoted 0 times
...
Jennie
2 months ago
I agree, A) Evaluation of proposals are much simpler.
upvoted 0 times
...
Raylene
2 months ago
I think A is the correct answer.
upvoted 0 times
...
...
Arthur
2 months ago
But with a cost reimbursable contract, the owner doesn't control all aspects of the work, so D) doesn't make sense.
upvoted 0 times
...
Alfred
2 months ago
I disagree, I believe the correct answer is A) Evaluation of proposals are much simpler.
upvoted 0 times
...
Malcolm
2 months ago
Evaluation of proposals being simpler? Sounds like a trap to me. I'll go with D - owner controls all aspects of the work.
upvoted 0 times
Alisha
30 days ago
So, the correct answer is D - owner controls all aspects of the work.
upvoted 0 times
...
Ettie
1 months ago
I don't think that's it, C is actually an advantage of a cost reimbursable contract.
upvoted 0 times
...
Sarina
1 months ago
But what about C - an early start can be made?
upvoted 0 times
...
Karon
2 months ago
I think you're right, D does seem like the best choice.
upvoted 0 times
...
Tiera
2 months ago
I agree, the owner controlling all aspects of the work is not an advantage.
upvoted 0 times
...
Nobuko
2 months ago
Definitely not an advantage, it limits the contractor's flexibility.
upvoted 0 times
...
Galen
2 months ago
I think D is the correct answer too.
upvoted 0 times
...
...
Arthur
3 months ago
I think the answer is D) Owner controls all aspects of the work.
upvoted 0 times
...
Alison
3 months ago
Hmm, I thought cost reimbursable contracts were all about flexibility, but I guess the owner has a lot of control too. Interesting...
upvoted 0 times
Nenita
2 months ago
D) Owner controls all aspects of the work
upvoted 0 times
...
Lisha
2 months ago
C) An early start can be made
upvoted 0 times
...
Richelle
2 months ago
B) Provides flexibility in dealing with changes
upvoted 0 times
...
Julie
2 months ago
A) Evaluation of proposals are much simpler
upvoted 0 times
...
...

Save Cancel