Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam CCP Topic 2 Question 15 Discussion

Actual exam question for AACE International's CCP exam
Question #: 15
Topic #: 2
[All CCP Questions]

You are reporting the following Earned Value Analysis information for the project:

EV= $1,500,000

AC=$1.000,000

PV= $2,000,000

What is the status of the project?

Show Suggested Answer Hide Answer
Suggested Answer: C

The problem provides key metrics used in Earned Value Management (EVM):

Earned Value (EV): $1,500,000

Actual Cost (AC): $1,000,000

Planned Value (PV): $2,000,000

Key Points:

Schedule Performance Index (SPI):

SPI = EV / PV = $1,500,000 / $2,000,000 = 0.75

An SPI less than 1 indicates the project is behind schedule.

Cost Performance Index (CPI):

CPI = EV / AC = $1,500,000 / $1,000,000 = 1.5

A CPI greater than 1 indicates the project is under budget.

Conclusion: The correct answer is C. Project is behind schedule, but under budget because the SPI indicates a delay in schedule, and the CPI shows that the project is currently spending less than planned.


Contribute your Thoughts:

Veta
26 days ago
Hmm, sounds like the project manager is trying to juggle too many things at once. I'll go with Option B, the one that makes the most sense.
upvoted 0 times
Lachelle
5 days ago
I agree, Option B seems like the most logical choice.
upvoted 0 times
...
Felix
11 days ago
I think the project is behind schedule and over budget.
upvoted 0 times
...
...
Goldie
1 months ago
Woah, this project is like a roller coaster - behind schedule but still spending too much! Option B is the way to go.
upvoted 0 times
Loren
10 days ago
It's definitely not looking good for this project, being behind schedule and over budget.
upvoted 0 times
...
Craig
11 days ago
I agree, option B seems to be the most accurate given the information provided.
upvoted 0 times
...
...
Rosendo
1 months ago
So, the answer would be B) Project is behind schedule, but over budget.
upvoted 0 times
...
Virgie
1 months ago
I agree, the PV is higher than EV.
upvoted 0 times
...
Shasta
1 months ago
I think the project is behind schedule.
upvoted 0 times
...
Erin
1 months ago
The project is behind schedule, but over budget. Option B is the correct answer.
upvoted 0 times
Kate
7 days ago
Project is behind schedule, but over budget. Option B is the correct answer.
upvoted 0 times
...
Crissy
8 days ago
PV= $2,000,000
upvoted 0 times
...
Geraldine
10 days ago
AC=$1.000,000
upvoted 0 times
...
Polly
13 days ago
EV= $1,500,000
upvoted 0 times
...
Glynda
15 days ago
We need to take corrective actions to get back on track.
upvoted 0 times
...
Jospeh
20 days ago
That's right, the project is not going as planned.
upvoted 0 times
...
Twana
29 days ago
So, the correct answer is option B.
upvoted 0 times
...
Wenona
1 months ago
The project is behind schedule, but over budget.
upvoted 0 times
...
...

Save Cancel