You are reporting the following Earned Value Analysis information for the project:
EV= $1,500,000
AC=$1.000,000
PV= $2,000,000
What is the status of the project?
The problem provides key metrics used in Earned Value Management (EVM):
Earned Value (EV): $1,500,000
Actual Cost (AC): $1,000,000
Planned Value (PV): $2,000,000
Key Points:
Schedule Performance Index (SPI):
SPI = EV / PV = $1,500,000 / $2,000,000 = 0.75
An SPI less than 1 indicates the project is behind schedule.
Cost Performance Index (CPI):
CPI = EV / AC = $1,500,000 / $1,000,000 = 1.5
A CPI greater than 1 indicates the project is under budget.
Conclusion: The correct answer is C. Project is behind schedule, but under budget because the SPI indicates a delay in schedule, and the CPI shows that the project is currently spending less than planned.
Veta
26 days agoLachelle
5 days agoFelix
11 days agoGoldie
1 months agoLoren
10 days agoCraig
11 days agoRosendo
1 months agoVirgie
1 months agoShasta
1 months agoErin
1 months agoKate
7 days agoCrissy
8 days agoGeraldine
10 days agoPolly
13 days agoGlynda
15 days agoJospeh
20 days agoTwana
29 days agoWenona
1 months ago