Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam CCP Topic 2 Question 15 Discussion

Actual exam question for AACE International's CCP exam
Question #: 15
Topic #: 2
[All CCP Questions]

You are reporting the following Earned Value Analysis information for the project:

EV= $1,500,000

AC=$1.000,000

PV= $2,000,000

What is the status of the project?

Show Suggested Answer Hide Answer
Suggested Answer: C

The problem provides key metrics used in Earned Value Management (EVM):

Earned Value (EV): $1,500,000

Actual Cost (AC): $1,000,000

Planned Value (PV): $2,000,000

Key Points:

Schedule Performance Index (SPI):

SPI = EV / PV = $1,500,000 / $2,000,000 = 0.75

An SPI less than 1 indicates the project is behind schedule.

Cost Performance Index (CPI):

CPI = EV / AC = $1,500,000 / $1,000,000 = 1.5

A CPI greater than 1 indicates the project is under budget.

Conclusion: The correct answer is C. Project is behind schedule, but under budget because the SPI indicates a delay in schedule, and the CPI shows that the project is currently spending less than planned.


Contribute your Thoughts:

Veta
2 months ago
Hmm, sounds like the project manager is trying to juggle too many things at once. I'll go with Option B, the one that makes the most sense.
upvoted 0 times
Billy
28 days ago
Let's hope they can get the project back on track.
upvoted 0 times
...
Tricia
1 months ago
The project manager needs to reassess their priorities.
upvoted 0 times
...
Lachelle
1 months ago
I agree, Option B seems like the most logical choice.
upvoted 0 times
...
Felix
1 months ago
I think the project is behind schedule and over budget.
upvoted 0 times
...
...
Goldie
2 months ago
Woah, this project is like a roller coaster - behind schedule but still spending too much! Option B is the way to go.
upvoted 0 times
Loren
1 months ago
It's definitely not looking good for this project, being behind schedule and over budget.
upvoted 0 times
...
Craig
1 months ago
I agree, option B seems to be the most accurate given the information provided.
upvoted 0 times
...
...
Rosendo
2 months ago
So, the answer would be B) Project is behind schedule, but over budget.
upvoted 0 times
...
Virgie
2 months ago
I agree, the PV is higher than EV.
upvoted 0 times
...
Shasta
3 months ago
I think the project is behind schedule.
upvoted 0 times
...
Erin
3 months ago
The project is behind schedule, but over budget. Option B is the correct answer.
upvoted 0 times
Kate
1 months ago
Project is behind schedule, but over budget. Option B is the correct answer.
upvoted 0 times
...
Crissy
1 months ago
PV= $2,000,000
upvoted 0 times
...
Geraldine
1 months ago
AC=$1.000,000
upvoted 0 times
...
Polly
2 months ago
EV= $1,500,000
upvoted 0 times
...
Glynda
2 months ago
We need to take corrective actions to get back on track.
upvoted 0 times
...
Jospeh
2 months ago
That's right, the project is not going as planned.
upvoted 0 times
...
Twana
2 months ago
So, the correct answer is option B.
upvoted 0 times
...
Wenona
2 months ago
The project is behind schedule, but over budget.
upvoted 0 times
...
...

Save Cancel