BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam CCP Topic 1 Question 8 Discussion

Actual exam question for AACE International's CCP exam
Question #: 8
Topic #: 1
[All CCP Questions]

Which of the following best describes the three key participants for projects that are executed under a three-party contractual relationship?

Show Suggested Answer Hide Answer
Suggested Answer: C

In construction and project management, a three-party contractual relationship typically involves three key participants: the Owner, the Engineer, and the Contractor.

Key Points:

Owner:

The entity that funds and owns the project. The owner defines the project scope, objectives, and requirements and is the ultimate decision-maker.

Engineer:

Often referred to as the 'Designer' or 'Consultant,' the engineer is responsible for the technical design and specifications of the project. They ensure the project is constructed according to the owner's requirements and standards.

Contractor:

The party responsible for executing the construction work. The contractor follows the design provided by the engineer and delivers the project within the agreed terms of the contract.

Conclusion: The correct answer is C. Owner, engineer, contractor because these three parties are central to the execution and management of construction projects under a three-party contractual arrangement.


Contribute your Thoughts:

Gracia
27 days ago
Haha, this is a tricky one! I'm going with Option C, though. The owner, engineer, and contractor - that's the holy trinity of construction, right?
upvoted 0 times
Leah
1 days ago
Definitely, they each play a crucial role in the project's execution.
upvoted 0 times
...
Abel
13 days ago
I agree, those three are essential for a successful project.
upvoted 0 times
...
Buck
14 days ago
I think Option C is correct. The owner, engineer, and contractor are the key participants.
upvoted 0 times
...
...
Elbert
27 days ago
I'm not sure, but I think A) Contracting officer, contractor, and contractor project manager could also be correct.
upvoted 0 times
...
Norah
1 months ago
I agree with Corazon, because the owner, engineer, and contractor are the key participants in project execution.
upvoted 0 times
...
Arlette
1 months ago
Ah, the classic three-party contract question! Option C is the way to go, my friends. The owner, engineer, and contractor - that's the holy trinity of project management!
upvoted 0 times
...
Theresia
1 months ago
I'm torn between Options C and D, but I think C is the better choice. The three key roles make more sense for a three-party contract.
upvoted 0 times
Hyun
10 days ago
Yes, Option C makes the most sense. The owner, engineer, and contractor are the key participants in projects executed under a three-party contract.
upvoted 0 times
...
Pamela
1 months ago
I think Option C is the most logical choice as well. It aligns with the typical roles involved in a three-party contractual relationship.
upvoted 0 times
...
Lorean
1 months ago
I agree, Option C seems to be the best choice. The roles of owner, engineer, and contractor make sense for a three-party contract.
upvoted 0 times
...
...
Marylyn
1 months ago
Option C seems to be the correct answer. The three key participants are the owner, engineer, and contractor, as they are typically involved in a three-party contractual relationship.
upvoted 0 times
Justa
18 days ago
Definitely, it's important for all three parties to work together effectively.
upvoted 0 times
...
Deeanna
19 days ago
That makes sense, they each play a crucial role in the project.
upvoted 0 times
...
Jesusa
22 days ago
Yes, the owner, engineer, and contractor are the key participants in a three-party contractual relationship.
upvoted 0 times
...
Gertude
1 months ago
I think option C is the correct answer.
upvoted 0 times
...
...
Corazon
2 months ago
I think the answer is C) Owner, engineer, contractor.
upvoted 0 times
...

Save Cancel