Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam CCP Topic 1 Question 19 Discussion

Actual exam question for AACE International's CCP exam
Question #: 19
Topic #: 1
[All CCP Questions]

Develop a CPM method considering the below tasks and logical relationships. Use this information to answer the related questions.

What is the late finish date of activity 50?

Show Suggested Answer Hide Answer
Suggested Answer: D

To determine the late finish date of Activity 50 using the CPM method, you would consider the latest finish times of its successors. The path through the project network would lead to the calculation that the latest possible time that Activity 50 can finish without delaying the project is Day 37. Therefore, the correct answer is D. Day 37.

Top of Form

Bottom of Form


Contribute your Thoughts:

Dexter
25 days ago
Ah, the eternal debate of CPM. I say we just flip a coin and move on to the next question. Who needs logic when you have luck?
upvoted 0 times
Johnathon
4 days ago
I agree, it seems like the logical choice.
upvoted 0 times
...
Ligia
7 days ago
I think the late finish date of activity 50 is Day 37.
upvoted 0 times
...
Nan
11 days ago
Let's not leave it up to chance, we can figure this out.
upvoted 0 times
...
...
Aja
1 months ago
This exam question is a real brain-teaser, but I'm confident the answer is Day 38. Gotta love those critical path puzzles!
upvoted 0 times
Tori
19 days ago
Yes, it's definitely Day 38. Those critical path puzzles can be tricky, but once you figure it out, it's so satisfying!
upvoted 0 times
...
Tori
20 days ago
I think you're right, the late finish date of activity 50 is Day 38.
upvoted 0 times
...
...
Leslie
1 months ago
Hmm, that makes sense. I'll go with Day 38 as well.
upvoted 0 times
...
Kandis
1 months ago
I believe it is Day 38 because of the logical relationships in the CPM method.
upvoted 0 times
...
Leslie
1 months ago
I think the late finish date of activity 50 is Day 37.
upvoted 0 times
...
Magnolia
1 months ago
Day 47? Really? That's way off. This question is a piece of cake, if you know your CPM.
upvoted 0 times
...
Kirby
2 months ago
Hmm, I'm going with Day 28. The time calculations seem straightforward, and that's the latest finish date I can see.
upvoted 0 times
Ashleigh
18 days ago
I'm going with Day 38. I need to review the task dependencies again to be sure.
upvoted 0 times
...
Oneida
21 days ago
I agree with Day 28. It seems to be the most logical choice based on the CPM method.
upvoted 0 times
...
Eden
24 days ago
I'm leaning towards Day 37. I need to double-check the relationships between the tasks.
upvoted 0 times
...
Alishia
1 months ago
I think it's Day 28 too. The logic behind the calculations makes sense.
upvoted 0 times
...
...
Trina
2 months ago
I'm not so sure about that. I think the correct answer is Day 37. The network diagram looks a bit tricky, but if you follow the logic, that's the right answer.
upvoted 0 times
...
Ettie
2 months ago
The late finish date of activity 50 is definitely Day 38. I think the critical path analysis clearly shows that.
upvoted 0 times
Fannie
6 days ago
Let's double-check the CPM method to be sure, but I think you're right about Day 38.
upvoted 0 times
...
Carin
7 days ago
I agree with you, the late finish date of activity 50 is Day 38.
upvoted 0 times
...
Lezlie
11 days ago
I'm pretty confident it's Day 38. The critical path analysis supports that.
upvoted 0 times
...
Meaghan
24 days ago
Are you sure about that? I think it's actually Day 37.
upvoted 0 times
...
...

Save Cancel