Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam CCP Topic 1 Question 18 Discussion

Actual exam question for AACE International's CCP exam
Question #: 18
Topic #: 1
[All CCP Questions]

In a fixed price contract the:

Show Suggested Answer Hide Answer
Suggested Answer: C

In a fixed-price/lump-sum contract, the agreed price is fixed and generally not subject to adjustment based on fluctuations in costs, unless explicitly stated in the contract terms. Payment for adjustments in construction costs due to fluctuations in resource prices or delays is typically not allowed unless there is a specific provision for such adjustments, which is rare in fixed-price contracts. Therefore, the correct answer is C. In no situation.

Top of Form

Bottom of Form


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel