Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam CCP Topic 1 Question 17 Discussion

Actual exam question for AACE International's CCP exam
Question #: 17
Topic #: 1
[All CCP Questions]

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Select the statement that best describes the method to estimate the cost of the new rides:

Show Suggested Answer Hide Answer
Suggested Answer: C

The problem provides key metrics used in Earned Value Management (EVM):

Earned Value (EV): $1,500,000

Actual Cost (AC): $1,000,000

Planned Value (PV): $2,000,000

Key Points:

Schedule Performance Index (SPI):

SPI = EV / PV = $1,500,000 / $2,000,000 = 0.75

An SPI less than 1 indicates the project is behind schedule.

Cost Performance Index (CPI):

CPI = EV / AC = $1,500,000 / $1,000,000 = 1.5

A CPI greater than 1 indicates the project is under budget.

Conclusion: The correct answer is C. Project is behind schedule, but under budget because the SPI indicates a delay in schedule, and the CPI shows that the project is currently spending less than planned.


Contribute your Thoughts:

Nathan
3 days ago
I think the best method to estimate the cost of the new rides is to break down the technology into components.
upvoted 0 times
...

Save Cancel