Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam CCP Topic 1 Question 17 Discussion

Actual exam question for AACE International's CCP exam
Question #: 17
Topic #: 1
[All CCP Questions]

You are reporting the following Earned Value Analysis information for the project:

EV= $1,500,000

AC=$1.000,000

PV= $2,000,000

What is the status of the project?

Show Suggested Answer Hide Answer
Suggested Answer: C

The problem provides key metrics used in Earned Value Management (EVM):

Earned Value (EV): $1,500,000

Actual Cost (AC): $1,000,000

Planned Value (PV): $2,000,000

Key Points:

Schedule Performance Index (SPI):

SPI = EV / PV = $1,500,000 / $2,000,000 = 0.75

An SPI less than 1 indicates the project is behind schedule.

Cost Performance Index (CPI):

CPI = EV / AC = $1,500,000 / $1,000,000 = 1.5

A CPI greater than 1 indicates the project is under budget.

Conclusion: The correct answer is C. Project is behind schedule, but under budget because the SPI indicates a delay in schedule, and the CPI shows that the project is currently spending less than planned.


Contribute your Thoughts:

Shala
9 days ago
I think the correct answer is C. The project is behind schedule, as the EV is less than the PV, but it's under budget, since the AC is less than the EV. Reminds me of that old saying, 'Better late than never, and cheaper than expected!'
upvoted 0 times
...
Werner
11 days ago
So, the answer is B) Project is behind schedule, but over budget.
upvoted 0 times
...
Fernanda
13 days ago
Hmm, this is a tough one. I'm leaning towards option D, as the project seems to be ahead of schedule but under budget. The EV is less than the PV, which means it's ahead of schedule, and the AC is less than the EV, so it's under budget. Gotta love these Earned Value questions!
upvoted 0 times
...
Precious
25 days ago
I'm going with option B. The project is behind schedule and over budget. The EV is less than the PV, so it's behind schedule, and the AC is greater than the EV, so it's over budget. Simple as that.
upvoted 0 times
...
Salina
27 days ago
This is a tricky one. Based on the information given, I would say the project is behind schedule but under budget. The EV is less than the PV, indicating the project is behind schedule, but the AC is less than the EV, suggesting it's under budget. Option C seems like the correct answer to me.
upvoted 0 times
Ardella
1 days ago
I agree, option C seems to be the correct answer based on the Earned Value Analysis information.
upvoted 0 times
...
Earleen
16 days ago
I agree, the EV is less than the PV, but the AC is less than the EV.
upvoted 0 times
...
Ria
17 days ago
I think the project is behind schedule but under budget.
upvoted 0 times
...
Latrice
20 days ago
I think the project is behind schedule but under budget.
upvoted 0 times
...
...
Lou
27 days ago
I agree, the PV is higher than EV.
upvoted 0 times
...
Jose
1 months ago
I think the project is behind schedule.
upvoted 0 times
...

Save Cancel