Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam AACE-PSP Topic 4 Question 34 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 34
Topic #: 4
[All AACE-PSP Questions]

If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Barbra
5 hours ago
I think historical production rates can be used.
upvoted 0 times
...

Save Cancel