Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam AACE-PSP Topic 4 Question 30 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 30
Topic #: 4
[All AACE-PSP Questions]

What day would Activity C complete if the duration of Activity A was reduced by five days?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Chantay
1 months ago
Alright, I've got my calculator and a fresh cup of coffee. Time to crunch the numbers and see what the correct answer is.
upvoted 0 times
Marvel
2 days ago
C) 45
upvoted 0 times
...
Kirk
11 days ago
B) 30
upvoted 0 times
...
Marcelle
20 days ago
A) 35
upvoted 0 times
...
...
Jodi
2 months ago
Wait, reducing the duration of Activity A? That's like trying to lose weight by cutting off your foot. Let's hope the exam isn't full of these kinds of logic puzzles!
upvoted 0 times
Nakisha
11 days ago
I agree, let's hope the exam is more straightforward than this question.
upvoted 0 times
...
Nicolette
13 days ago
I think it's B) 30. That's my best guess.
upvoted 0 times
...
Maddie
19 days ago
I know, right? It seems like a strange way to calculate completion dates.
upvoted 0 times
...
...
Eun
2 months ago
Okay, let's see. If Activity A is shortened, that could push the completion of Activity C forward. I'll try to work this out step-by-step.
upvoted 0 times
Aaron
3 days ago
So, it seems like the completion of Activity C is directly affected by the duration of Activity A.
upvoted 0 times
...
Kristeen
10 days ago
If Activity A is reduced by ten days, then Activity C would complete on day 30.
upvoted 0 times
...
Selma
19 days ago
But what if it's reduced by ten days instead?
upvoted 0 times
...
Freeman
2 months ago
I think if Activity A is reduced by five days, Activity C would complete on day 35.
upvoted 0 times
...
...
Carey
2 months ago
I'm not sure, but I think the answer is B) 30 as well. It makes sense logically.
upvoted 0 times
...
Lazaro
2 months ago
I agree with Adaline, because if Activity A is reduced by 5 days, it would finish on Day 30.
upvoted 0 times
...
Kerry
2 months ago
Hmm, reducing the duration of Activity A seems like it would affect the entire project timeline. I'll have to think this through carefully.
upvoted 0 times
Daron
15 days ago
D) 40
upvoted 0 times
...
Fannie
21 days ago
C) 45
upvoted 0 times
...
Tabetha
22 days ago
B) 30
upvoted 0 times
...
Clorinda
22 days ago
A) 35
upvoted 0 times
...
...
Adaline
3 months ago
I think the answer is B) 30.
upvoted 0 times
...

Save Cancel