BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25%
- Ends In
00:00:00
Coupon code:
SAVE25
X
Welcome to Pass4Success
Login
|
Sign up
-
Free
Preparation Discussions
Mail Us
support@pass4success.com
Location
US
MENU
Home
Popular vendors
Salesforce
Microsoft
Nutanix
Amazon
Google
CompTIA
SAP
VMware
Fortinet
PeopleCert
Eccouncil
HP
Palo Alto Networks
Adobe
ServiceNow
Dell EMC
CheckPoint
Linux Foundation
Discount Deals
New
About
Contact
Login
Sign up
Home
Discussions
AACE International Discussions
Exam AACE-PSP Topic 4 Question 15 Discussion
AACE International Exam AACE-PSP Topic 4 Question 15 Discussion
Actual exam question for AACE International's AACE-PSP exam
Question #: 15
Topic #: 4
[All AACE-PSP Questions]
How could the structural steel drawing delay have been prevented?
A
Add a time buffer at the end of structural steel activities.
B
Allow adequate time for review and resubmittal in the baseline schedule.
C
Release the structural steel for fabrication concurrent with review of structural steel shop drawings.
D
Switch to post-tensioned concrete construction.
Show Suggested Answer
Hide Answer
Suggested Answer:
A
by
Carisa
at
Jun 30, 2024, 05:41 PM
Limited Time Offer
25%
Off
Get Premium AACE-PSP Questions as Interactive Web-Based Practice Test or PDF
Contribute your Thoughts:
Submit
Cancel
Malcom
3 months ago
Option A? Time buffer? Sounds like someone's trying to add more time to their vacation. Let's stick to the basics, folks.
upvoted
0
times
...
Mike
3 months ago
Hmm, I'd go with B. It's the safest option, and you can't go wrong with good old-fashioned planning.
upvoted
0
times
Lynette
2 months ago
User 3
upvoted
0
times
...
Ula
2 months ago
User 2
upvoted
0
times
...
Shawana
3 months ago
User 1
upvoted
0
times
...
...
Martina
3 months ago
D? Really? Switching to post-tensioned concrete? That's overkill, just plan for the review process properly.
upvoted
0
times
...
Christoper
3 months ago
C seems like a risky move. You don't want to start fabrication before the drawings are approved, that's just asking for trouble.
upvoted
0
times
Brock
2 months ago
D) Switching to post-tensioned concrete construction could be a drastic change.
upvoted
0
times
...
Alva
3 months ago
C) I agree, releasing the structural steel for fabrication before approval is risky.
upvoted
0
times
...
Phillip
3 months ago
B) Allow adequate time for review and resubmittal in the baseline schedule.
upvoted
0
times
...
Ciara
3 months ago
A) Add a time buffer at the end of structural steel activities.
upvoted
0
times
...
...
Kris
3 months ago
Switching to post-tensioned concrete construction might have been a drastic but effective solution to prevent delays.
upvoted
0
times
...
Cherry
4 months ago
I think option B is the way to go. Allowing enough time for review and resubmittal is crucial to avoid delays.
upvoted
0
times
Asuncion
3 months ago
I think adding a time buffer at the end of structural steel activities could also help.
upvoted
0
times
...
Caren
3 months ago
I agree, option B is definitely important to prevent delays.
upvoted
0
times
...
...
Maile
4 months ago
I believe releasing the structural steel for fabrication concurrent with review could have also prevented the delay.
upvoted
0
times
...
Willie
4 months ago
I agree with Rusty, having some extra time at the end would have helped.
upvoted
0
times
...
Rusty
4 months ago
I think adding a time buffer at the end could have prevented the delay.
upvoted
0
times
...
Log in to Pass4Success
×
Sign in:
Forgot my password
Log in
Report Comment
×
Is the comment made by
USERNAME
spam or abusive?
Commenting
×
In order to participate in the comments you need to be logged-in.
You can
sign-up
or
login
Save
Cancel
Malcom
3 months agoMike
3 months agoLynette
2 months agoUla
2 months agoShawana
3 months agoMartina
3 months agoChristoper
3 months agoBrock
2 months agoAlva
3 months agoPhillip
3 months agoCiara
3 months agoKris
3 months agoCherry
4 months agoAsuncion
3 months agoCaren
3 months agoMaile
4 months agoWillie
4 months agoRusty
4 months ago