Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam AACE-PSP Topic 3 Question 8 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 8
Topic #: 3
[All AACE-PSP Questions]

Which of the following is NOT true?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Natalie
9 months ago
That's true. I think I might change my answer to B) Constraints can interfere with the longest path calculation.
upvoted 0 times
...
Nettie
10 months ago
Well, let's think about it. Constraints can definitely interfere with the longest path calculation.
upvoted 0 times
...
Tenesha
10 months ago
I'm leaning towards C) Multiple calendars can affect the total float calculation.
upvoted 0 times
...
Natalie
10 months ago
I disagree, I believe the answer is A) Remaining durations can exceed original durations.
upvoted 0 times
...
Nettie
10 months ago
I think the correct answer is D) A network must contain only one Critical Path.
upvoted 0 times
...
Carin
10 months ago
I'm pretty sure the answer is D because each project can contain multiple Critical Paths.
upvoted 0 times
...
Tamra
11 months ago
I'm torn between B and C as the answer.
upvoted 0 times
...
Dana
11 months ago
I believe the answer is C.
upvoted 0 times
...
Crista
11 months ago
I disagree, I think the answer is A.
upvoted 0 times
...
Erasmo
11 months ago
I think the answer is D.
upvoted 0 times
...
Laquanda
1 years ago
Agreed. Option B is a solid one. Now, option C... Multiple calendars can affect the total float calculation. That makes sense to me.
upvoted 0 times
...
Leonard
1 years ago
You make a good point. Option A seems a bit shaky. Let's move on to option B. Constraints can definitely interfere with the longest path calculation. That's a core concept in critical path analysis.
upvoted 0 times
...
Beatriz
1 years ago
Hmm, I'm not so sure about that. Doesn't the remaining duration have to be less than or equal to the original duration? Otherwise, how would we be able to complete the project on time?
upvoted 0 times
...
Margurite
1 years ago
Okay, let's start with option A. I think remaining durations can exceed original durations, right? That seems like a pretty straightforward concept.
upvoted 0 times
...
Arminda
1 years ago
Yeah, I agree. The wording is a bit convoluted. Let's go through this step by step and see if we can figure it out.
upvoted 0 times
...
Carlota
1 years ago
This question seems a bit tricky. I'm not sure if I fully understand the implications of each answer option.
upvoted 0 times
Latricia
10 months ago
A) Remaining durations can exceed original durations.
upvoted 0 times
...
Reuben
11 months ago
C) Multiple calendars can affect the total float calculation.
upvoted 0 times
...
Mitzie
11 months ago
B) Constraints can interfere with the longest path calculation.
upvoted 0 times
...
...

Save Cancel