Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Pete
6 hours ago
I think the answer is B) 1000, 1001, and 6001.