BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam AACE-PSP Topic 2 Question 12 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 12
Topic #: 2
[All AACE-PSP Questions]

How could the structural steel drawing delay have been prevented?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Vannessa
5 months ago
Option C is like playing structural steel Tetris. I wouldn't want to be the one responsible for that gamble.
upvoted 0 times
...
Catherin
5 months ago
I'm going with B. Proactive planning is key to avoiding delays in a project like this.
upvoted 0 times
Beckie
4 months ago
C) Release the structural steel for fabrication concurrent with review of structural steel shop drawings.
upvoted 0 times
...
Oretha
4 months ago
C) Release the structural steel for fabrication concurrent with review of structural steel shop drawings.
upvoted 0 times
...
Rossana
4 months ago
I agree with B. Proactive planning is crucial to prevent delays.
upvoted 0 times
...
Isaac
4 months ago
I agree, proactive planning is essential to prevent delays.
upvoted 0 times
...
Rachael
4 months ago
B) Allow adequate time for review and resubmittal in the baseline schedule.
upvoted 0 times
...
France
4 months ago
B) Allow adequate time for review and resubmittal in the baseline schedule.
upvoted 0 times
...
Annice
4 months ago
A) Add a time buffer at the end of structural steel activities.
upvoted 0 times
...
Isadora
5 months ago
A) Add a time buffer at the end of structural steel activities.
upvoted 0 times
...
...
Golda
5 months ago
C is an interesting idea, but it's a risky move. You might end up with a lot of rework if the drawings aren't approved.
upvoted 0 times
...
Martha
5 months ago
D? Really? That's a bit extreme, don't you think? Switching construction methods is a huge undertaking.
upvoted 0 times
...
Matthew
5 months ago
Option B seems like the obvious choice here. You need to plan for that review process upfront.
upvoted 0 times
Ressie
4 months ago
Yeah, planning for review and resubmittal time is crucial in preventing delays.
upvoted 0 times
...
Marica
4 months ago
I agree, adding a time buffer at the end would have helped.
upvoted 0 times
...
Mariann
4 months ago
B) Allow adequate time for review and resubmittal in the baseline schedule.
upvoted 0 times
...
Josphine
5 months ago
Switching to post-tensioned concrete construction could have been a drastic but effective solution.
upvoted 0 times
...
Kattie
5 months ago
A) Add a time buffer at the end of structural steel activities.
upvoted 0 times
...
Devora
5 months ago
I think releasing the structural steel for fabrication concurrent with review of shop drawings would have been more efficient.
upvoted 0 times
...
Rodolfo
5 months ago
I agree, adding a time buffer at the end of structural steel activities could have helped.
upvoted 0 times
...
...

Save Cancel