BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam AACE-PSP Topic 1 Question 7 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 7
Topic #: 1
[All AACE-PSP Questions]

If Activity E's duration changes to 4 months, what is the overall duration of the project.

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Hubert
4 months ago
I think it should be 21 months. Changing Activity E might have ripple effects on other activities.
upvoted 0 times
...
Bulah
4 months ago
But based on our initial estimates, what do you think the overall duration should be?
upvoted 0 times
...
Maryann
4 months ago
Hmm, I'm not sure. I need to calculate the critical path to confirm the overall duration.
upvoted 0 times
...
Rickie
4 months ago
I agree with Juan, changing Activity E to 4 months should make the project last 20 months.
upvoted 0 times
...
Juan
4 months ago
I think the overall duration would be 20 months if Activity E changes to 4 months.
upvoted 0 times
...
Bulah
4 months ago
If Activity E's duration changes to 4 months, what is the overall duration of the project?
upvoted 0 times
...
Samira
5 months ago
I believe the overall duration might be 20 months if Activity E's duration changes to 4 months.
upvoted 0 times
...
Omer
5 months ago
So, if it changes to 4 months, do we think the overall duration will be 20 months or 21 months?
upvoted 0 times
...
Lindsay
5 months ago
I agree, if Activity E's duration is extended, it will definitely impact the overall duration.
upvoted 0 times
...
Vincent
6 months ago
I think the overall duration of the project will be increased if Activity E takes longer.
upvoted 0 times
...
Samira
6 months ago
If Activity E's duration changes to 4 months, the overall project duration will be affected.
upvoted 0 times
...

Save Cancel