What is the free float for Activity F?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Maryanne
4 months ago
Because Activity F can be delayed by 2 months without affecting the project completion date.
upvoted 0 times
...
Hubert
4 months ago
Why do you think it's 2 months?
upvoted 0 times
...
Maryanne
4 months ago
I disagree, I believe the free float for Activity F is 2 months.
upvoted 0 times
...
Thurman
4 months ago
Ha! This is a trick question. The answer is clearly C) 1 month. Everyone knows that's the standard unit of time for free float, right? *wink wink*
upvoted 0 times
...
Hubert
4 months ago
I think the free float for Activity F is 0 months.
upvoted 0 times
...
Tabetha
4 months ago
Hmm, I'm not so sure about that. The image shows some kind of schedule, and Activity F seems to have some wiggle room. I'm going to go with D) 2 months.
upvoted 0 times
...
Chara
4 months ago
I'm pretty sure the answer is B) 0 months. The critical path doesn't include Activity F, so its free float should be 0.
upvoted 0 times
Raina
4 months ago
Yes, that makes sense. The critical path determines the free float for activities.
upvoted 0 times
...
Wilda
4 months ago
I think you're right. The free float for Activity F should be 0 months.
upvoted 0 times
...
...